5.1 Whitianga Esplanade Waterfront Redevelopment
YouTube time stamp for this item:10.20am
Transition Support, Allan Tiplady was in attendance for this item.
The Board was updated on the future redevelopment of the Whitianga Esplanade Waterfront area.
Mr Tiplady tabled two attachments, omitted from the report.
- Attachment D - Whitianga Esplanade Waterfront Redevelopment advisory group Terms of Reference.
- Attachment E - Project Plan Summary.
It was noted the Board had spent a lot of time and contributed to the detail of the project and requested a detailed presentation be made to the new incoming Board, for the next triennial.
Resolved:
That the Mercury Bay Community Board:
1. Receives the 'Whitianga Esplanade Waterfront Redevelopment' report dated 13 July 2022.
2. Recommends to Council to continue to progress investigations into the redevelopment of the Whitianga Esplanade Waterfront area to identify the most efficient and effective way of alleviating current health and safety issues and to provide for growth in the activities currently taking place in the area.
3. Recommends to Council that the following objectives for the Whitianga Esplanade Waterfront area be approved:
a. Creation of a trailer boat launching and parking area physically separated from the other activities undertaken on the Esplanade Waterfront area. This could be in the Esplanade Waterfront area or at an alternative location.
b. A grassed recreation area, which, if a boat ramp is retained in the area, is able to be utilised as an overflow trailer boat parking area in the peak summer period.
c. The area of any trailer boat parking and grassed recreation area providing for the annual Whitianga Oceans (formerly Scallop) Festival.
d. A separate pontoon area and “finger” pontoons, to provide for the tourist boat and charter fishing boat operators, with an associated parking area.
e. Provision for recreational fishing.
f. A separate public play and beachfront area incorporating a playground, a beach to swim from, a swimming platform, a jetty / pontoon (with some elevation) to jump from into the water.
g. A dedicated Whitianga Ferry berth.
h. A separate pontoon / jetty for the Game Fishing Club use.
i. The existing public toilet.
j. Linkages from the ferry pontoon and public area to the Esplanade cafes and restaurants and the town centre via Taylors Mistake.
k. The existing wharf becoming a separate wharf for commercial fishing without public access
4. Recommends to Council that a subgroup of the Community Board be established to make recommendations to the Community Board, to be known as the Whitianga Esplanade Waterfront Redevelopment Advisory Group with membership to be made up of:
a. Two Mercury Bay Community Board members, to be appointed by Council.
b. Two Ngāti Hei appointees.
c. One Whitianga Marina Society appointee
5. Recommends to Council that the terms of Reference for the Governance Group as attached to the report to the Mercury Bay Community Board meeting on 13th July 2022 be approved.
6. Recommends to Council that the 2021/2022 Annual Plan budget of $111,835 for Esplanade Waterfront investigations be carried forward to the 2022/2023 year.
7. Recommends to Council that the unspent 2021/22 Annual Plan budget of $131,000 for Whitianga Esplanade Waterfront improvement works be carried forward to identify and undertake any immediate, economically viable, actions that could be implemented to mitigate current health and safety issues.
8. Recommends to Council that it be noted that staff resourcing will be required to take the lead on the whole project to ensure the outcomes are delivered and that the engagement of external consultants will be required to provide the expertise for the wide range of tasks to be investigated, reported and delivered.
9. Recommends to Council that the project plan summary as attached to the report to the Mercury Bay Community Board Meeting on 13 July 2022 be approved for implementation.
10. Recommends to Council that the following project budget be submitted for inclusion in the 2023/24 Annual Plan and in the next review of the Long Term Plan.
- 2022/23, $137,200
- 2023/24, $162,000
- 2024/25, $288,000
- 2025/26, $76,000
11. Recommends to Council that the capital development budget currently included in the Long Term Plan be retained and be reconsidered at the appropriate stage as the project progresses and updated costs and funding are available.
Moved/seconded by: Fox/MMcLean